You're planning a new driveway or a patio for the spring, and somewhere between the measuring tape and the first quote the permit question came up. Maybe a friend said Denver doesn't care about flatwork, or a bid didn't mention a permit at all, and you're not even sure you need one. Mostly you'd rather not pour a slab the city later says you shouldn't have.
The answer in Denver depends less on the concrete than on where it sits and whether it's changing size. A patio on your own lot, or a driveway replaced at the same size, doesn't need a permit. A driveway that's new or wider than the old one, and new work where it meets the street, are a different story.
Most of the slab on your own lot doesn't need a building permit
Would you pull a permit for a small driveway?
In Denver, a patio or driveway poured at grade on your own property doesn't need a building permit, because the city's building code exempts flatwork that sits no more than 30 inches above the ground. Replacing a driveway at the same size doesn't need a permit either. A driveway that's new or wider than the old one usually needs a zoning permit, and new work in the public right of way, such as a new curb cut or a wider apron, needs a right-of-way permit from the city.
The building permit exemption is in section 130.3 of the Denver Building Code, which lists flatwork, including sidewalks and driveways, with walking surfaces no more than 30 inches above grade, as work that doesn't need a building permit. The catch is that it can't sit over a basement or a room below, and it can't be part of an accessible route. A backyard patio poured on the ground behind a Park Hill bungalow fits that easily. A raised patio built up over a retaining edge, or a slab that roofs over a basement window well, may not.
Exempt doesn't mean anything goes. The city says plainly that work without a permit still has to meet code, so the slab still has to drain away from the house and respect the zoning rules for your lot.
Where Denver does ask for a permit
The first place is zoning. Denver's own permit table says a driveway from the street that is new or expanded needs a zoning permit, and so does a new or expanded driveway off the alley if it sits in the front setback. A driveway that comes off the alley and stays out of the front setback needs no permit at all, which is good news in the older parts of town. Plenty of homes in Park Hill, Berkeley, Baker and Washington Park have narrow drives running back to a garage off the alley, and replacing one of those on your own lot needs no city paperwork.
Zoning also caps how much of the front yard can be paved. On single-family lots in Denver's urban neighborhood zone districts, parking and driveway paving in the front setback is limited to 16 feet wide or 33 percent of that area, so turning a single drive into a wide two-car pad out front often isn't allowed. Check that cap before you get attached to a layout, since a permit can't get you past it.
The second place is the street end. A concrete driveway usually crosses city property before it reaches the road: the apron, the curb cut and the stretch of public sidewalk in between. When a job adds to that strip, with a new curb cut, a wider apron or new sidewalk, Denver wants a right-of-way construction permit with a street occupancy permit alongside it, both filed through the city's E-Permits system, and the work has to be done by a contractor holding a Denver right-of-way license. Moving a curb cut or changing where the driveway meets the street goes further, to a review by city transportation engineers who also look at the sidewalk, curb ramps and alley next to it.
Replacing the same driveway in the same spot
This is the most common job, and the simplest. Replacing a driveway at the same size, in the same spot, doesn't need a permit in Denver. The city's permit table asks for a zoning permit only when a driveway is new or expanded, and a straight tear-out and repour is neither. Most Denver driveway replacements include the apron, because that's the section mag chloride and the plow hit hardest, and we covered why in only the first ten feet of my driveway is falling apart.
So the question that matters on a replacement is whether anything changes size or shape. If the driveway gets wider, the curb cut moves or the apron grows, that's when zoning or the city's right-of-way office gets involved. If it goes back the way it was, there's no permit to pull. Since voters passed Denver Deserves Sidewalks in 2022, the city has been taking over repair of public sidewalks, paid for by an annual sidewalk fee, so a heaved sidewalk panel out front may be the city's job rather than yours, a point we went into in am I liable if someone trips on my walkway.
If you live outside Denver proper
Each city in the metro writes its own rules, and they don't line up. Aurora's homeowner guide says a like-for-like driveway replacement doesn't need a permit, while widening one does, and its front yards are capped at 40 percent concrete. Lakewood exempts private walks and driveways under 30 inches above grade but treats the apron between the curb and a detached sidewalk as public way work. Broomfield says on-grade patios need no permit, and that a new driveway may need a public improvement permit for the part in the right of way.
Highlands Ranch adds a second layer. Douglas County handles the right of way, and the Highlands Ranch Community Association reviews exterior changes through its architectural committee. A like-for-like driveway replacement in the same size, material and finish doesn't need that approval, while an expansion does and is limited to nine extra feet of width. Patios and walks may need it too, so send the plan in over the winter, well before the April start of pour season.
What to ask before anyone pours
Ask who pulls the permits and get the answer in writing. On our jobs, Miguel Bañuelos, the licensed Colorado contractor who does our work, pulls any permits the job needs, and that's built into the price. When we quote a driveway, Miguel measures on site first and we look at where the slab meets the street, because that's where the rules change and each city in the metro handles that strip its own way. We check what your city requires before we quote anything, so the fixed, itemized price you get covers the job as it has to be done.
Settle these before you sign with anyone:
Whether the job adds to or changes the apron, curb, alley or public sidewalk, and who is filing the city permit for that part.
Whether the new slab is the same size as the old one, or wider, because wider is what usually brings zoning or HOA review into it.
Whether your HOA wants plans first. In Highlands Ranch, and anywhere else with an architectural committee, that approval can take longer than the city's.
Patios are the simpler half of this. A backyard slab on grade, away from the street, rarely needs a permit in Denver, so your time is better spent on the base, the reinforcement and the drainage, which we cover on the concrete patios page.
Planning a spring driveway now
Late fall is a good time to sort this out. Pour season here runs roughly April through October, and permit reviews, HOA committees and a contractor's spring calendar all fill up at the same time, so having the paperwork question answered by March gets you a place in line. Our work is done by Miguel's licensed and insured crew, pouring in the metro since 2010, and since Miguel comes out to measure himself, he can tell you on the spot whether your job needs a permit at all.
If you're weighing a new or replacement driveway and want the permit picture for your address before you commit, call us at (720) 782-8086 and we'll come out, measure, and tell you what your city will want to see.